5. Monitoring Commitments- Commitments Made in the Initial Project Description Appendix (APM-REP-05000-0217-R000)

Detailed Technical Assessment Report • Ref: REC-NSP7-PURO

Section Synopsis

Pages: 1226-1232

The provided text outlines the Nuclear Waste Management Organization's (NWMO) monitoring and engagement framework for a proposed Deep Geological Repository (DGR). It details commitments to environmental monitoring across all project phases, including a tentative 70-year extended monitoring period post-operation. The document emphasizes adaptive management to address uncertainties and highlights a reconciliation-based approach to engagement, specifically focusing on the Wabigoon Lake Ojibway Nation (WLON) and the Township of Ignace. Key commitments include seeking Free, Prior, and Informed Consent (FPIC), integrating Indigenous Knowledge, and adhering to federal and provincial regulatory standards for air, water, and soil protection.

Community Assessment Narrative

The submission exhibits a professional and structured tone, yet it contains a notable tension between its assertions of 'high confidence' and the admission that quantitative modelling of effects is incomplete. This creates a transparency gap; the proponent asks reviewers to trust in 'proven practices' before the specific impacts of this unique project are fully quantified. While the commitment to a 70-year monitoring period is significant, the deferral of its specific scope until the end of the operations phase—decades into the future—limits the ability of current regulators and stakeholders to evaluate the adequacy of long-term safety verification.

Ethically, the explicit commitment to Free, Prior, and Informed Consent (FPIC) and the recognition of WLON sovereignty are progressive. However, the text lacks clarity on the procedural 'off-ramps' should consent be withdrawn or if monitoring reveals impacts that exceed the capacity of adaptive management. The reliance on 'adaptive management' as a primary tool for addressing uncertainty can sometimes be used to bypass rigorous pre-emptive mitigation planning. Furthermore, while the document mentions 'other Indigenous groups' and 'interested parties,' the level of detail provided for their engagement is significantly less robust than that for the primary host communities, suggesting a potential gap in regional consultation depth.

Corrective Measures & Recommendations

The proponent should provide a preliminary conceptual framework for the 70-year extended monitoring program during the current impact assessment phase, rather than deferring it to the end of operations. This framework should identify the specific thermal, seismic, and radiological indicators that will be used to confirm repository safety before final sealing. Providing this detail early would substantiate the 'high confidence' claim and allow for a more rigorous scientific review of the long-term closure plan.

Additionally, the NWMO should formalize the process for integrating Indigenous Knowledge (IK) with technical modeling, particularly for resolving potential contradictions between the two. A clear protocol should be established that defines how IK will influence project design and what specific 'social determinants of health' will be monitored. This would move the commitment from a high-level policy statement to a measurable, accountable component of the Environmental Protection Program, ensuring that community well-being is tracked with the same rigor as biophysical indicators.

On 16 February, 2026 the Impact Assessment Agency of Canada (IAAC), with input from the Canadian Nuclear Safety Commission (CNSC), published a Summary of Issues (SOI) for the proposed Deep Geological Repository (DGR) for Canada’s Used Nuclear Fuel Project, put forward by the Nuclear Waste Management Organization (NWMO). The SOI identifies the key issues that IAAC considers relevant to the federal integrated impact assessment process for the project. NWMO’s response to the SOI will assist IAAC in determining whether an impact assessment is required under section 16 of the Impact Assessment Act. If an impact assessment is required, the issues outlined in the SOI—together with NWMO’s response—will help shape the scope of the assessment and inform the continued development and finalization of the Integrated Tailored Impact Statement Guidelines and associated plans.

Alignments to IAAC Summary (SOI)

The analysis of Melgund Township’s public comments reveals a high degree of alignment with the IAAC Summary of Issues (SOI) published on February 16, 2026. Specifically, the community’s concern regarding the deferral of the 70-year extended monitoring scope directly supports the IAAC’s identified issue under the theme of "Monitoring and institutional control," which highlights the need for transparency in monitoring methods and intergenerational stewardship. Melgund’s technical observation that a lack of defined success criteria hinders long-term safety assessments validates the Agency’s focus on the "suitability of host rock for long-term containment" and "radiological effects to the environment."

Furthermore, Melgund’s critique of the proponent’s "high confidence" in mitigation measures—despite incomplete quantitative modeling—aligns with the IAAC’s section on "Accidents and Malfunctions," specifically the "High uncertainty novel project" theme. The community’s finding that the proponent may be relying on reactive adaptive management rather than proactive protection echoes the IAAC’s concerns regarding the "effectiveness of proposed mitigation measures" and the "novel nature of the project" described in Annex A. This suggests a shared skepticism regarding the proponent's ability to predict long-term outcomes without finalized data.

In the realm of social and cultural impacts, Melgund’s identification of a gap in "social determinants of health" metrics aligns with the IAAC’s "Human Health and Well-Being" and "Socio-Economic Conditions" sections. The community’s call for specific baseline data for mental and physical health supports the IAAC’s requirement for "community-led baseline data collection" and addresses "psychosocial health impacts." Additionally, Melgund’s concern regarding the "conditional" integration of Indigenous Knowledge provides a specific technical example of the broader issue raised in the IAAC’s "Indigenous engagement" section regarding how such knowledge is "considered, incorporated, and reflected in project planning."

Recommendations

The recommendations put forward by the community working group focus on moving the proponent’s commitments from high-level policy statements to measurable, accountable frameworks. By demanding a preliminary conceptual framework for the 70-year monitoring program during the current assessment phase, the working group seeks to address the "Monitoring and institutional control" issues identified by the IAAC. This recommendation ensures that thermal, seismic, and radiological indicators are established early, providing the scientific rigor necessary to substantiate safety claims before the project proceeds to phases where reversal or modification becomes more difficult.

Additionally, the recommendation to formalize a protocol for integrating Indigenous Knowledge (IK) with technical modeling directly addresses the IAAC’s concerns regarding "Indigenous engagement" and "Respect for Indigenous authority." By establishing a clear methodology for resolving potential contradictions between western science and traditional knowledge, the community ensures that the "social determinants of health" are tracked with the same precision as biophysical indicators. This approach bridges the gap between the IAAC’s identified need for better baseline data and the proponent’s currently vague promises, ensuring that community well-being is a central, quantifiable, and accountable component of the Environmental Protection Program.

Key Claims

Environmental monitoring will verify predicted effects and measure compliance with permit conditions.
Extended monitoring at repository depth is planned for approximately 70 years post-operation.
There is a high level of confidence in proposed mitigation measures despite incomplete quantitative modelling.
The NWMO will seek the free, prior, and informed consent (FPIC) of impacted peoples of WLON.
Adaptive management will be used to address uncertainties and improve risk management outcomes.

Underlying Assumptions

Established regulatory standards and proven practices are sufficient to mitigate risks for a deep geological repository.
A 70-year monitoring window is an appropriate duration to confirm long-term safety before final sealing.
Indigenous Knowledge can be effectively integrated into technical safety assessments when permission is granted.
The hosting agreements with WLON and Ignace will sufficiently address the socio-economic and environmental concerns of those communities.

Critical Observations & Gaps

Analysis Table
Issue Identified Implication Information Required
The scope of extended monitoring is deferred until the end of the Operations phase. The lack of a defined scope for the 70-year monitoring period makes it difficult to assess the long-term safety of the decommissioning phase. A preliminary list of monitoring parameters and success criteria for the decommissioning phase.
Vague commitment to 'understand and address social determinants of health.' Without specific indicators, the commitment to address social determinants of health remains an abstract promise. Specific metrics and baseline data for mental health, physical health, and community well-being.
High confidence in mitigation despite incomplete quantitative modelling. Relying on adaptive management for unquantified effects may lead to reactive rather than proactive environmental protection. The completed quantitative modelling results to validate the proposed mitigation measures.
Integration of Indigenous Knowledge is conditional and lacks a clear methodology for reconciliation with western science. The conditional use of Indigenous Knowledge ('when given permission') creates uncertainty about how it will be weighted against technical data. A formal framework or protocol for the co-application of Indigenous Knowledge and technical modeling.

Working Group Recommendations

Environment

Challenge the Proponent to define specific environmental triggers and immediate mitigation protocols for 'road wash-out' events that could isolate the site or the community.

In Table 5-1 of the Proponent's submission, monitoring of culverts and roadside ditches is proposed to limit the risk of road wash-outs. In the context of Melgund, a road wash-out is not merely a sediment control issue; it is a critical infrastructure failure that would sever access for emergency responders from distant regional hubs. The community has no local capacity to manage such events. By demanding specific triggers and a commitment to 100% self-sufficient repair capacity, the Working Group ensures that environmental failures do not become human safety catastrophes. This recommendation provides an advantage to the project by ensuring that the Proponent's 'adaptive management' approach includes hard engineering solutions for maintaining access, which is vital for the long-term viability of the site in a remote, unorganized township.
ENV-145
Human Environment (People)

Request a technical evaluation of the proposed Highway 17 intersection designs to ensure they prioritize unimpeded access for regional emergency vehicles traveling from Dryden and Ignace.

The Initial Project Description mentions ongoing discussions with the Ministry of Transportation regarding connection options at Highway 17. For the residents of Melgund, this highway is the only artery for life-saving services. Any project-related traffic congestion or poorly designed intersections could delay emergency response times from distant hubs, which is a life-safety issue given the lack of local services. This task is an opportunity for the Proponent to improve the project by integrating 'emergency priority' into their infrastructure design. The expected result is a transportation plan that guarantees project activities will not degrade the already precarious emergency access for the unorganized territory, thereby aligning the project's physical footprint with its stated commitment to community well-being.
HEP-193
Human Environment (People)

Demand the Proponent provide a comprehensive Emergency Services Self-Sufficiency Plan that accounts for the total absence of local fire, police, and ambulance services in Melgund Township.

The Proponent's submission references the 'safety of the system' and 'social determinants of health' as key commitments, yet it fails to acknowledge that Melgund Township is an unorganized territory with zero local emergency capacity. Relying on distant regional hubs like Ignace or Dryden for emergency response creates an unacceptable risk profile for both project personnel and local residents. This recommendation is critical because it forces the Proponent to move beyond vague safety commitments and demonstrate how they will provide 100% of the required emergency capacity internally. By addressing this gap early, the Proponent can improve project safety margins and reduce the potential burden on overstretched regional services, ultimately fostering greater community trust and ensuring that a local incident does not escalate due to delayed response times from distant municipalities.
HEP-194
Environment

Require the Proponent to provide a conceptual framework for the 70-year extended monitoring period, specifically identifying the thermal and radiological indicators that will be tracked post-operation.

The Proponent's submission defers the scope of the 70-year extended monitoring program until the end of the Operations phase. For a community like Melgund, which lacks a permanent municipal government to oversee long-term corporate commitments, this deferral creates significant uncertainty regarding intergenerational safety. Establishing these Valued Components (VCs) now allows the community to understand what 'safety' looks like in the long term. This is an opportunity for the Proponent to substantiate their 'high level of confidence' in the repository's performance with concrete, measurable parameters. The expected result is a more robust baseline that includes long-term environmental stability indicators, providing the community with the transparency required to evaluate the project's legacy.
ENV-146

Understanding the Impacts of Nuclear Waste on our Community

This digital archive houses the public comments submitted to the Impact Assessment Agency of Canada regarding Project 88774: The Nuclear Waste Management Organization Deep Geological Repository (DGR) for Canada's Used Nuclear Fuel Project. The impact assessment is led jointly by the Impact Assessment Agency of Canada and the Canadian Nuclear Safety Commission. This archive preserves community perspectives, concerns, and observations shared during the assessment process, particularly in relation to Melgund Township, Northwestern Ontario and the communities of Dyment and Borups Corners who are the closest and most impacted of all in the process.